Haverhill Pavilion Behavioral Health
A phased interior renovation of approximately 40,000 square feet, completed around active facility operations with controlled work areas, protection of existing conditions, and six interior trades self-performed through turnover.
The challenge
A behavioral health hospital of approximately 40,000 square feet had to be renovated while it remained in operation. The building could not be emptied, so the scope had to be delivered in phases the facility could release without disrupting patient care.
Stage by stage
Each stage of the work, in order. Frames marked Illustration show that type of work; the photographs of the finished spaces are our own.
Illustration01 · Preconstruction
Before any crew arrived, we worked with the facility to divide the scope into phases it could release one at a time—keeping patient areas protected, operational, and on schedule.
Illustration02 · Protection
Temporary barriers, dust control, and a protected circulation route were in place before demolition began in each phase, so occupied units on the other side stayed in service.
Daily coordination with facility operations covered access, shutdowns, and deliveries.
Illustration03 · Framing and board
Demolition, metal stud framing, and drywall were self-performed by our own crews, so each phase moved from open walls to finished board without waiting on another subcontractor.
Illustration04 · Ceilings and finishes
Acoustic ceilings, flooring, tile, doors, hardware, wall protection, and painting followed with the same crews, with bathroom renovation, repairs, and punch work closing out each phase.
Completed
Our own photographs of the completed project, area by area.
01 · 5 photographs
Staff stations under curved wood soffits, with solid-surface counters, patterned feature panels, and a blue floor inset marking each one.





02 · 7 photographs
Dining and group rooms with durable plank flooring, acoustic ceilings, tamper-resistant furniture, and large printed nature murals.







03 · 4 photographs
Patient rooms with built-in platform beds and cubbies under full-wall murals, and a shower room with grab bars and a linear floor drain.




04 · 5 photographs
Corridors, a waiting room, a staff work room, and the exterior courtyard.





Trades we self-performed